Variations & Quotes
Managing subcontractor quotes and variation orders within the project budget.
5 min readUpdated 2026-04-19Developer Projects
The Variations & Quotes module manages the flow of subcontractor pricing and approved variation orders. It maintains a running budget impact summary and integrates with the Payment Claims module.
Requesting a Quote
- 1Navigate to the Variations tab within your project.
- 2Click Request Quote.
- 3Enter: package/trade description, scope of works, and the date by which the quote is required.
- 4Select the subcontractor from the project members list or enter a new contact.
- 5Click Send. The subcontractor receives an email notification with the quote request.
Processing Variation Orders
- 1When a variation event occurs (design change, unforeseen condition, scope addition), click New Variation.
- 2Link the variation to the relevant contract or subcontract.
- 3Enter: variation description, reason (design change / latent condition / scope addition), and estimated cost.
- 4Submit to the principal contractor or client for approval.
- 5Once approved, the variation value is added to the project contract sum and reflected in the payment schedule.
Variation Approval
Never instruct work that has not been formally approved as a variation. Verbal instructions are not enforceable under most NZ construction contracts (NZS 3910, NZS 3915). All variations should be submitted in writing and signed off before work proceeds.